Automatic Process order type not picking in CR01

$
0
0

Hi friedns,

 

i have created new Production scheduler-030 for plant -  0101  through - CORU and CORY t.codes and we are not assigning the

Prod. sched. profile in Materail master.

 

Now while creating the new process order through CR01,system is not picking automatically process order type for new production scheduler -030 and new prodction schedulre already assign in material master .

 

For old Production scheduler-010 process order type is picking automatically for same plant.

 

Are there any user exit need to update.

 

Please advise.

 

Thank you.

 

Regards.