RemOrdPlan not getting transferred to Available Budget in PS

$
0
0

Hi Experts,

 

The scenario goes like this.

Budgeting is activated for our project profile.Availability control is active.

Original budget allocated for INR 50,000 against the WBS "WBSE-1"

A Service Activity is created under this WBS with "short text-Installation charges"- Qty - 1PU.

Service lines for Item-1:

1.Desktop Installation - 50Nos - INR200.

 

So total PR Valuation price =INR 10,000.

Present Budget Status is below:

 

Original Budget(INR)CommittmentRemOrd PlanActualAssigned(INR)Available(INR)
50,00010,0000010,00040,000


PO is created against the PR.

Price of service line is changed to INR 190/Nos. So, PO Value =INR9,500.

Budget status after PO creation:

Original Budget(INR)CommittmentRemOrd PlanActualAssigned(INR)Available(INR)
50,0009,500500010,00040,000

Now,Service Entry is done only for 35Nos=INR6,650

Budget Status after the service Entry:

 

Original Budget(INR)CommittmentRemOrd PlanActualAssigned(INR)Available(INR)
50,0002850500665010,00040,000

Now, I want to go for Short close of the PO for the left out 15Nos in service lines.

After shortclosing the PO, Budgte status is shown below.

 

Original Budget(INR)CommittmentRemOrd PlanActualAssigned(INR)Available(INR)
50,00003350665010,00040,000

 

The Value in  the RemOrdPlan should be moved to Available Budget for further Planning.

How this can be achieved?

The Project is still Live.

This Network cannot be closed as other Purchases are active.

Waiting for your valuable suggestion.

Thanks,

Krishna